Dubai’s new Al Maktoum airport to run a year of trials before first passengers

The Arabic Reporter Newsroom · November 22, 2026 · 20:16 · 3 MIN READ

The new passenger terminal at Al Maktoum International Airport (DWC) will be tested for at least a year without travellers before it opens, Dubai Airports chief executive Paul Griffiths told reporters in Dubai on Tuesday, November 17, according to The National, Gulf News and Khaleej Times.

The trial period will cover baggage handling, check-in, Wi-Fi and other airport systems, Griffiths said. “There will be at least a year of testing before we even allow the first customer to cross the threshold,” he was quoted as saying by The National. The first phase of the airport, in the south of the emirate, is due to open in 2032.

A $35 billion construction site

Griffiths described DWC as “definitely a live project”, saying more than 100,000 workers are on site, piling has begun and groundworks are well advanced on a development budgeted at about $35 billion (128 billion dirhams). Major contracts, including those for the baggage-handling system and automated people movers, are under discussion, he said.

Dubai Airports said in August that 13 billion dirhams of contracts were under way at DWC, with a further 55 billion dirhams due to be awarded before the end of 2026, Khaleej Times recalled. In June, Dubai Aviation Engineering Projects reported that more than 17,000 concrete piles had been installed and over 45 million cubic metres of earth excavated, according to Gulf News.

The first phase will give the new terminal an annual capacity of 150 million passengers. When fully built, with five runways, the airport is planned to handle 260 million passengers and 12 million tonnes of cargo a year.

Moving an entire airport 70 km south

The operator will run Dubai International (DXB) and DWC in parallel for a period before consolidating operations at the new site, about 70 kilometres away. Griffiths said the move would be several times larger than Hong Kong’s relocation of its main airport in the 1990s, which involved around 20 million passengers. “That’s never been done on that scale,” he said.

He added that the shift goes far beyond aviation infrastructure, as staff living in Dubai’s northern districts and the Northern Emirates will not be able to commute daily, requiring new residential communities for airport-sector workers. “The whole city has got to move,” he said, adding that recruiting and training the extra staff needed is one of the biggest challenges ahead. The future of the DXB site, he noted, is a decision for the government.

Check-in away from the terminal

Griffiths also told Khaleej Times that city terminals are being discussed, allowing passengers to check in at a metro station, a hotel or another location in the city before travelling to DWC, although he gave no timeline. Dubai has approved a City Terminal Project under its Dubai 10X initiative, and the Roads and Transport Authority has invited consultants to design a proposed 55-kilometre Airport Express Line linking DXB and DWC, the newspaper reported.

New technologies will be tried first at DXB before being introduced at the larger airport, Griffiths said, stressing that the operator cannot afford delays. “We cannot be late,” he said.